HANSON CONSTRUCTION MATERIALS PTY LIMITED CONCRETE CARRIERS CONTRACT
DETERMINATION
INDUSTRIAL RELATIONS
COMMISSION OF NEW SOUTH WALES
Application by Hanson
Construction Materials Pty Ltd, industrial organisation of employers.
(No. IRC 6774 of 2004)
Before Mr Deputy
President Sams
|
27 April 2004
|
DETERMINATION
Index
Clause No. Subject Matter
1. Definitions
2. Area
Incidence and Duration
3. Term of
Contracts of Carriage
4. Assignment
of Contracts of Carriage
5. Cartage
Rates
6. Safety
Net
7. Cartage
Accounts
8. Living
away from Home Allowance
9. Statutory
Requirements and Insurance
10. Loading
11. Hazardous
Approach to Job Site
12. Availability
of a Suitable Vehicle
13. Responsibility
for Load
14. Breakdowns
15. Two-Way
Radio and GPS Equipment
16. Provision
of Mixer
17. Mixer Care
and Maintenance
18. Painting
and/or Signwriting of the Mobile Unit
19. Manning
20. Uniforms
21. Amenities
22. Fleet Size
23. Commitment
to Training
24. Disputes
Procedure
25. Rostering
26. Plant
Stored Carrier's Equipment
27. Business
Viability
28. Occupational
Health and Safety
29. Environment
Protection and Pollution Control
30. Contractor's
Subsidiary Companies
1. Definitions
1.1 For the
purpose of this Contract Determination the following terms shall bear the
meaning:
The Act shall mean - the Industrial Relations Act 1996
(NSW)
Award shall mean - the Transport Industry - Mixed
Enterprises (State) Award as varied from time to time.
Concrete shall mean - a product whether mixed, blended
or batched, that contains but not limited to as a minimum: cement, aggregate,
sand and water; mortar containing cement sand and water; grout containing
cement, sand and water; slurry containing cement and water; or binders
containing cement and sand. This
definition is not contingent on the method of production, laying or description
of the finished product.
Continuous Pours shall mean -
(a) A slab and any
walls, columns, stairs and the like, provided they are an integral part of the
said slab and are poured at the same time;
(b) Road
pavements; or
(c) Multiple strip
footings within a radius of 1/2 kilometre.
All other work is excluded as a continuous pour.
Contract of Carriage shall have the meaning defined in
the Act.
Contract Carrier or Carrier shall mean - a single
operator owner driver trading as an incorporated body (where the operator owner
driver is a director and controlling shareholder of the incorporated body) who
is engaged under a contract of carriage with the Principal Contractor as
defined.
Contractor shall mean - Principal Contractor as defined
in the Act. The Principal Contractor in this Contract Determination is Hanson
Construction Materials Pty. Ltd.
Country means - the area outside the Sydney
Metropolitan Area as defined and within New South Wales.
Cyclic roster shall mean:
(a) a roster made
up of truck numbers, which dictates the selection of a particular vehicle for a
function and is addressed from the first truck number to the last;
(b) when the
roster has been fully addressed the roster then changes so that the truck
number that was first becomes last.
Each truck number is moved up one position in turn, and so on; and
(c) Each Carrier
will start the day, when not rostered off, in order of a single cyclic roster
and thereafter in order of his return to plant.
Mini truck shall mean- a truck with an agitator that
has a mixing capacity of 2.8 m3 or less.
Mixer shall also mean - Agitator and vice versa.
Sydney Metropolitan Area is, for the purpose of this
Contract Determination, limited to the area in which concrete is produced and
delivered within the following boundaries:
Stanwell Tops, Bulli, Mt. Ousley, Appin, Razorback,
Warragamba, Emu Plains, Sackville, Hawkesbury Bridge, Terry Hill, Palm Beach
(See Schedule H).
Union shall mean - the Transport Workers' Union of New
South Wales which term includes the Ready mixed Concrete Executive Committee of
the Union.
Written Authority shall mean - any approved document
that bears the signature of the Carrier or the Contractor as the case may be.
1.2 Interpretation
Words importing the singular number shall include the
plural number and words importing the plural number shall include the singular
number.
The masculine gender shall include the feminine and
neuter genders.
2. Area Incidence and
Duration
(a) This Contract
Determination contains all of the rights and obligations of the Contractor and
Carriers. The Contractor is hereby exempted from the Transport Industry
Concrete Haulage Contract Determination.
(b) This Contract
Determination shall take effect on and from 1st November 2004 and shall remain
in force for a period of three (3) years (unless varied by written agreement
prior to that time). Notation: This Contract Determination represents a ten
(10) year commitment by both parties. It is not the intention of either party
to vary that commitment.
3. Term of Contracts
of Carriage
3.1 Carriers shall
be granted Contracts of Carriage with the Contractor as follows:
(a) The term of
the Contact of Carriage shall be ten (10) years commencing on 1st November 2004
if the Carrier provides a truck:
(i) which is aged
between 0 and 4 years (for Sydney Metro) or between 0 and 8 years (for NSW
Country) as at 1 November 2003; and
(ii) which has a
gross carrying capacity of 22.5 tonnes (6wheelers) or 27.5 tonnes (8 wheelers).
(b) Where the
Carrier cannot provide a truck which is aged between 0 and 4 years (for Sydney
Metro) but is able to provide a truck which is aged between 4 and 8 years as at
1 November 2003 and otherwise complies with the requirements of sub-clause (ii)
above then the Carrier shall be granted a five (5) year Contract of Carriage.
Where the Carrier introduces a truck to the fleet which
meets the age criteria in sub clause (a) above and this introduction is
effected during the five (5) year contract period then that Carrier shall
receive a further five (5) year extension to make a total of a ten (10) year
contract.
Notation: the age of a truck is to be determined by
reference to the date upon which the vehicle was first registered.
(c) Where the
Carriers listed hereunder provide a truck which is capable of operating an
hydraulic agitator and is in a reasonable condition as determined by the
Contractor then the Carrier shall be granted a five (5) year Contract of
Carriage. The Carriers are:
PLC2265 at Moree
PLC2216 at Moree
PLC2295 at Gunnedah
PLC2232 at Blayney
PLC2223 at Cowra
(d) Notation: If
the NSW State Government introduce changes to the laws relating to truck
carrying capacities or legal loading limits then Carriers covered by this
Contract Determination may choose to modify or change their truck in order to
comply with the changed laws and take advantage of increased carrying
capacities. In any event all Carriers must provide trucks which comply with the
law as varied by the government from time to time.
3.2 Termination of
Contracts of Carriage
(a) From 1
November 2004 if the Contractor decides to terminate a contract of carriage for
any reason other than serious misconduct the Contractor shall pay to the
Carrier an immediate termination payment of $66,000.00 and the contract shall
terminate forthwith. In addition to the
termination payment the Contractor shall offer to purchase the truck owned by
the Carrier at the relevant market value at that time. The Carrier may choose to accept or reject
the offer of the Contractor.
(b) Where the
Contractor terminates a contract of carriage at any time by reason of serious
misconduct by the Carrier then the Contractor has the right to terminate the
contract without notice and without an obligation to make any compensation
payment to the Carrier. For the purposes of this Arrangement "serious
misconduct" may include acts of physical violence, serious theft, serious
threats made to a person, gross negligence.
(c) Where a
Carrier decides to leave the fleet and not invoke the provisions of Clause 4
Assignment of Contracts of Carriage then the Carrier must give the Contractor
no less than one (1) months notice of intention to leave. The Contractor and
the Carrier may negotiate a purchase by the Contractor of the Carrier’s truck
if they so choose.
4. Assignment of
Contracts of Carriage
4.1 For the period
between 1 November 2004 and 31 October 2005 any Carrier may assign the contract
of carriage on the open market provided that no more than three (3) Carriers
will be permitted to assign each calendar month. Thereafter Carriers with more
than 8 or more years service with the company or its predecessors in title may
assign on the open market on the following terms:
(i) the Carrier
has no obligation to first offer the contract for assignment to the Contractor;
(ii) the purchaser
introduced by the Carrier must be approved by the Contractor. Approval will not
be unreasonably withheld but the Purchaser will be required to pass a
pre-engagement medical and submit to a check of their previous work history;
(iii) the
assignment shall take place on the last business day of the relevant calendar
month;
(iv) no more than
eight (8) such assignments in Sydney Metro and eight (8) such assignments in NSW
Country shall be permitted to occur each year.
Note: The parties acknowledge that 12 long serving
carriers have already been given approval to assign their contracts of carriage
on the open market between 1st November 2004 and 31st October 2005 in addition
to that set out in clause 4.1.
4.2 If any Carrier
(other than those seeking to assign under the provisions of Clause 4.1 above)
seeks to assign their contract of carriage then the following procedure shall
apply:
(i) the Carrier
must first offer the contract to the Contractor. The offer must be in writing
and the Contractor has 28 days to consider its position and respond to the
offer.
(ii) If the
Contractor decides to accept the offer of the Carrier the purchase price shall
be deemed to be $66,000.00. Upon advising the Carrier of its decision to accept
the offer the Contractor shall pay the Carrier the said amount of $66,000.00
and the Carrier shall depart the fleet immediately. The Contractor shall also
offer to purchase the truck of the Carrier for the relevant market value at the
time and the Carrier may choose to accept the offer of the Contractor if the
Carrier so wishes.
(iii) If the
Contractor decides to reject the offer of the Carrier then the Contractor shall
advise the Carrier accordingly and the Carrier shall be free to assign the
contract on the open market.
(iv) Any purchaser
introduced by the Carrier must be approved by the Contractor. Approval will not
be unreasonably withheld but the Purchaser will be required to pass a
pre-engagement medical and submit to a check of their previous work history;
(v) the assignment
shall take place on the last business day of the relevant calendar month.
5. Cartage Rates
5.1 Cartage Rates
Payable to Carriers
(a) The Contractor
shall pay to a Carrier the utilisation cartage rates ("the utilisation
rates") set out in Schedule A hereto.
All transfers, and surcharges are included in rates as shown in Schedule
A with the exception of:
(i) transfers -
outside the Sydney metropolitan area;
(ii) surcharges -
Sundays, public holidays (or as otherwise agreed);
(iii) waiting time;
(iv) workshop
transfers in excess of 30 km
Notation: for transfers outside the Sydney Metropolitan
area and for workshop transfers the total distance travelled to and from the
plant/workshop shall be calculated less the first 30 kilometres of the trip
i.e. if the total distance travelled there and back is less than 30 kilometres
then no transfer shall be paid. If the
total distance travelled there and back is more than 30 kilometres then a
transfer will be paid for the total distance travelled.
(b) Utilisation
will be measured on a plant-by-plant basis. The Contractor shall not use a particular plant utilisation rate
as a means of disadvantaging another plant which may have a lower utilisation
rate. Utilisation for 8 wheeler vehicles will be calculated separately from 6
wheeler vehicles again on a plant-by-plant basis.
(c) On and from
1st November 2004 and on and from the 1st day of every subsequent six monthly
period (Sydney Metro) or every subsequent quarter (NSW Country) during the term
of the Contract of Carriage, the plant average utilisation rates as adjusted
for the previous quarter (calculated on a moving annual total basis) will be
payable by the Contractor to the Carrier.
(d) Notation: The
utilisation rates contained in Schedule A are graduated in measurements of 100
m3 and are paid to Carriers accordingly.
(e) The
utilisation rates paid are based on the plant average, and will exclude those
Carriers who have an availability less than ninety five percent (95%) of
required working days in the relevant quarter.
(f) The
utilisation rates applicable for Metropolitan carriers will be reviewed on 1st
May 2005 and thereafter each November and May based on increases or decreases
in the cost formula set out in the Rise and Fall Schedule annexed hereto (which
Schedule is at the front of Schedule A hereto).
The utilisation rates applicable for Country carriers
will be reviewed each quarter and adjusted in accordance with the May and
November review adjustments arising from the Metropolitan rates review.
(g) A minimum lead
of 3km shall apply at all times, however where a plant has an average cartage
distance of less than 5km then a minimum lead of 5km shall apply at that plant
(h) Country work
for metro carriers performing cartage outside the Sydney metro zone, it is
agreed that the 4500 m3 utilisation rate will apply.
5.2 Waiting Time
The Contractor shall pay Waiting Time to the Carriers
on the following basis:
(a) As a
fundamental obligation of this Contract, the Carrier must obtain a customer
signature on the delivery docket. If the customer does not sign the Carrier
must PRINT the name of the Carrier on the delivery docket and then the Carrier
must sign the docket clearly and legibly and note the reason for no customer
signature.
(b) Provided the
carrier complies with the obligation contained in the sub-clause above the
Contractor shall pay Waiting Time to the Carrier at the rate of $1.00 per
minute for each minute spent on site after the first 40 minutes for a load of
greater than three (3) cubic metres. If
the load is three (3) cubic metres or less, Waiting Time will apply at the rate
of $1.00 per minute for each minute spent on site after the first 30 minutes.
Time spent on site shall start at the arrival of the Carrier at the site in
question which time of arrival shall be measured by the time at which the
Carrier activates the Status Button in the vehicle of the Carrier.
Special Note: For 1 November 2004 to 1 February 2005
Metro Carriers will not be required to seek to communicate a charge to
customers for waiting time. However
from 1 February 2005 it shall be the obligation of all Carriers to charge
customers for waiting time in accordance with the procedure outline in Clause
5.2 (a) above.
(c) Waiting time
shall be paid to carriers in all situations where a carrier is required to
remain at a site in a blowback situation.
Waiting time shall apply from the time the carrier arrives at the site
until the time the carrier is able to depart the site.
5.3 Benefits
Included In The Cartage Rates
(a) The following
payments are provided for in the rates payable to Carriers under this Contract
Determination:
(i) All benefits
and entitlements under the Award; and
(ii) Leave
entitlements as follows:
(a) 20 days annual
leave and, in addition, the annual leave loading as prescribed in the Award;
(b) 10 public
holidays - New Year's Day, Australia Day, Good Friday, Easter Monday, Anzac
Day, Queen's Birthday, Labour Day, Christmas Day, Boxing Day, Union Picnic Day.
(c) 34.8 hours of
long service leave per annum.
(d) 64 hours sick
leave per annum in accordance with the Award.
(e) 16 hours
bereavement leave.
(f) RDO - 13 per
annum leave (10 days may be taken and the balance of 3 are paid in the rates)
(iii) Superannuation
at 9% or any subsequently legislated percentage rate.
(iv) The Carrier
must take the leave provided above.
(v) If the leave
requirements provided herein vary then this will be reflected in the cartage rate.
(b) Should the
Contractor require the Carrier to man the vehicle when on leave entitlements,
then in addition to the appropriate cartage rate the Contractor will pay to the
Carrier the difference between the labour portion of the cartage rate paid for
cartage in the relevant period and the actual amount paid to the relief driver
as per the Award for a casual driver.
5.4 Haulage Area,
Cartage Zones, and Transfer Fees
(a) The Carrier
shall haul concrete as required, from the Contractor's plants. Carriers shall
be assigned to plants at the commencement of this Arrangement and these plant
assignments shall be reviewed by the parties on a quarterly basis.
(b)
(i) Where a
vehicle is transferred outside the Sydney Metropolitan area with a load, that
distance which is in excess of the round trip distance as per 5.1(a) to the
plant in which the load was received shall be paid at the rate of "H"
per km (as indicated in Appendix X hereto) if applicable.
(ii) Where a
vehicle is transferred outside the Sydney Metropolitan area without a load, a
transfer fee of "H" per km shall be paid for distances in excess of
15km.
(c) Approved
travel to and from the workshop shall be paid at the rate of "G" per
km, if applicable.
5.5 Measurement of
Distance Travelled
Cartage payments shall be based on the shortest
distance to site. The distance shall be rounded up to the nearest whole
kilometre.
Any dispute arising in relation to distance travelled
must be resolved within twenty four (24) hours between the Contractor's representative
and the Carrier or his representative. Resolution of the dispute shall be on
the basis of the shortest practicable route available at the time of delivery.
5.6 Minimum Load
A Carrier shall be guaranteed a minimum load of 3 m3 or
a minimum payment on the basis of 3 m3.
5.7 Mixing in the
Yard
A fee of "C" per load shall be paid to mix
and discharge concrete into a customer's vehicle for transport from the plant
and subsequent placement outside the boundaries of the plant. Ex-plant mixes
shall be limited to completed orders not exceeding 3 m3.
5.8 Long Distance
Rates
Where the load is required to be carried in excess of:
(i) twenty five
(25) km then each additional km will be paid on the basis of a 4 m3 minimum
load; and
(ii) fifty (50) km
then each additional km will be paid on the basis of a 5m³ minimum load.
5.9 Standby Time
Where a Carrier is required by a Contractor to remain
at the plant to take a delivery to a job commencing after normal delivery
hours, for more than one hour, standby time will be paid at a rate of
"E" for each complete half hour following the expiration of the
initial hour.
Standby time is only applicable outside normal working
hours before receiving a load and also between loads. After the expiration of
one hour but only payable after each additional complete half hour, a Carrier
must be on standby for a minimum of eighty nine (89) minutes before being
entitled to a payment of "E".
Normal hours are 6.00 a.m. to 4.00 p.m. Monday to
Friday and 6.00 a.m. to 12.00 noon Saturday.
Example
A Carrier is required to remain at the plant until 6.00
p.m. on Monday evening. He receives his first load at 6.00 p.m. and returns to
the plant at 7.00 p.m. and is loaded again at 8.25 p.m. His entitlement in the
above example is:
4.00 p.m. to 5.00 p.m.
|
No payment (initial hour).
|
|
|
5.00 p.m. to 6.00 p.m.
|
Standby time of 2 x
"E"
|
|
|
Between 7.00 p.m. and 8.25
p.m.
|
No standby time.
|
However, should this second load have been batched at
8.30 p.m., his entitlement would be:
7.00 p.m. to 8.00 p.m.
|
No payment (initial hour).
|
|
|
From 8.00 p.m. to 8.30 p.m.
|
1 x "E"
|
5.10 Call-out Fee
A Carrier called back after normal delivery hours shall
receive a minimum of 8 x "E".
Until surcharges equal 8 x "E" the difference
between the surcharges paid and 8 x "E" will be paid to the driver as
a call-out fee.
Where a Carrier is called back and does not receive a
load after normal delivery hours, the Carrier shall be paid a call-out fee of 8
x "E".
5.11 Standby
Function
Where the Contractor knowingly requires a Carrier to
provide his vehicle at a plant which has a substantially reduced production
capability for a period not less than one (1) hour, then the Carrier will be
entitled to a standby function payment by the Contractor of "N" per
hour or part thereof.
5.12 Concrete
Produced for Contractor's Own Use
Where a Carrier is required to load concrete for the
Contractor's own use within the confines of the Contractor's concrete plant
where loaded, he will be paid at the rate of "O" per m3 with a
minimum of 3 m3, plus waiting time, if applicable.
5.13 Penalty Rates
Surcharge rates per m3 based on a minimum of 3 m3
payable in respect of concrete loaded which is completed during the following
hours shall be:
Saturday:
|
4.00 p.m. to)
|
|
Monday:
|
6.00 a.m.)
|
3 x "F"
|
|
|
|
Public Holidays:
|
|
3 x "F"
|
5.14 Multiple
Discharge Points
(a) Same Customer
Payment for haulage covers the total distance
travelled. Unloading time will commence
from the start of unloading at the first point and will continue until the
final completion of unloading when drops are within one km. Over one km, the
total of the additional km travelled will be added to the ticket and paid as if
the original load was carried for the entire distance plus waiting time, if
applicable, commencing from the arrival at the first delivery point.
(b) Multiple
Customers/Multiple Dockets
Each delivery will be treated for the purpose of
payment of cartage as if a separate delivery had been made from the plant to
each delivery point.
5.15 Diverted Loads
(a) Direct
Diversion
Where a load is diverted en-route a Carrier shall be
paid normal cartage rates covering the total distance travelled from initial
departure from the plant to the ultimate delivery point of the load, plus
waiting time payment whilst awaiting diversion advice.
(b) Return to
Plant and Divert
It is thereafter treated as a new load.
(c) Return to
Plant and Dumped
It shall be paid for as in Clause 5.17 (a)
(d) Return to
Plant and Subsequently Dumped Outside Plant
Where the Contractor directs ANY quantity of leftover
concrete that has been agitated in the yard to be taken to another site and
dumped, payment shall be made in accordance with the utilisation rate for the
respective area (with the respective minimum kilometres).
5.16 Leftover
Concrete
(a) All concrete
remains the property of the Contractor and accordingly the Contractor reserves
the right to direct where concrete is to be taken or if and where it is to be
dumped. The Carrier shall contact the plant for instructions as soon as
possible.
(b) A Carrier will
be paid for any returned load on the basis of a 3 m3 minimum for all quantities
3 m3 or below to a limit of 0.8m3 and at the appropriate rate for quantities
above 3 m3.
(c) When 3 m3 or
more of concrete is left over from a job, return cartage shall be paid at the
rate of 'B' with the exception of sub clause (i) (ii) (iii) and (iv) below
hereof.
(i) Where the
load is rejected because of product fault.
(ii) Where the
load taken out is not required.
(iii) When a truck
is used to dispose of leftover concrete, such as a result of a pump line
blowback.
(iv) When the
concrete is not returned to the "source" plant.
In all cases of sub clauses (i), (ii), (iii) and (iv)
above return cartage shall be paid at the rate of 'B' with a 3 m³ minimum,
provided that an amount equal to or in excess of 0.8 m³ is actually carried.
(d) When a Carrier
is required to agitate any quantity of concrete within the plant he will be
paid at the rate of "I" per minute after completion of the first 15
minutes whilst awaiting diversion advice.
(e) Where a
carrier is required to transfer left over concrete to Wallgrove then it shall
be paid as a new load.
5.17 Dumped Concrete
(a) Where the
Carrier is directed by the Contractor to dump concrete in the plant a dumping
fee of "M" will be paid upon the carrier dumping the concrete as
directed by the Contractor or if a Carrier is requested to "wash out"
when carrying a quantity of 0.8 m³ or greater.
(b) Where the
Carrier is required to dump concrete outside the plant then the carrier shall
be paid normal cartage rates for the load to be dumped.
5.18 Road and Bridge
Tolls
(a) The Contractor
shall provide to all Carriers an E-Way Toll Tag to be affixed in the truck. It
is the responsibility of the Carrier to advise the Contractor if the E-Way tag
fails in any way. If the Carrier does not advise the Contractor then the
Carrier will bear the responsibility for the cost of the tolls involved.
6. Safety Net
6.1 Safety Net for
Carriers with Ten (10) Year Contracts
(a)
(i) An earnings
safety net and guaranteed minimum earnings of $17,340 per quarter during the
term of the Contract of Carriage will apply.
The safety net will be administered on an annual basis,
in accordance with sub clause (iv) below, i.e. there will be adjustments up or
down from quarter to quarter, as appropriate.
Reviews will occur during April (with the result to apply from 1 May)
and October (with the result to apply from 1 November) each year. As at 1
November 2004 the current annual net earnings level below which a safety net
payment will be due is $69,359.
(ii) A Carrier who
earns less than $17,340 in a quarter is entitled to a make-up payment for that
quarter so that the earnings of the Carrier will equate to $17,340
(iii) The make-up
payment will be made in the pay period following the end of the relevant
quarter.
(iv) When a Carrier
has been paid a make-up payment under this Safety Net Scheme then the Carrier
is obliged to refund the make-up payment to the Contractor if the Carrier earns
more than the minimum level of earnings in the following quarter or quarters.
However at the end of the financial year (i.e. 30 June) the calculation ceases
and then a new year is deemed to begin. Calculations are not carried forward to
successive years. The contractor is duly authorised to deduct such safety net
make-up payments from the carrier’s remittance where applicable.
(v) The amount
referred to in (a) (i) above as the annual net earnings level will be adjusted
annually in accordance with movements in the rise and fall formula.
(b) When a Carrier
is "unavailable" (as explained in clause 6.1(d) his safety net will
be reduced by $241.00 per day for each day he is unavailable in that quarter to
a maximum of $17,340 per quarter. (As
adjusted as aforesaid in accordance with movements in the rise and fall formula
contained in Schedule A).
(c) The Contractor
and the TWU will agree on a mechanism so that the Contractor is not
disadvantaged by causes beyond its control and the Carrier is not disadvantaged
by actions of the Contractor.
(d) The normal
week covers six (6) days, Monday to Saturday inclusive but totals an amount of
288 days as listed in Schedule A. A
Carrier will not be deemed to be unavailable for the purposes of the safety net
guaranteed adjustment if:
(i) The nominated
plant is closed or unable to produce;
(ii) The agitator
is unserviceable, except by accidental damage by the Carrier;
(iii) The Carrier
is on approved annual leave (two (2) weeks per annum);
(iv) The Carrier
takes sick leave (eight (8) days per annum);
(v) The Carrier has
rostered day off (ten (10) days per annum); or
(vi) The Carrier is
notified the prior day that he is not required or is rostered off at the
direction of the Contractor.
(vii) The carrier
takes a gazetted public holiday
6.2 Safety Net for
Carriers with Five (5) Year Contracts Specified in Clause 3.1 (c)
The safety net scheme detailed in Clause 6.1 above
shall apply to these Carriers but on the basis that all figures used in Clause
6.1 shall be reduced by 50%. In all
other respects the provisions of Clause 6.1 above shall apply to these
Carriers.
7. Cartage Accounts
(a)
(i) The
Contractor shall prepare Recipient Created Tax Invoices ("RCTI's") in
accordance with dockets issued by the Contractor to the Carrier during the
course of the accounting period.
(ii) The RCTI’s,
as prepared by the Contractor, shall be itemised on a daily basis which will
include data, docket numbers, quantity of loads, kilometres, extra payments,
amount per load and job address.
(iii) All the above
items will be totalled individually at the conclusion of the accounting period.
The gross cartage figure should be shown, and any agreed deductions, e.g.
income adjustments, fully itemised and a net figure then shown.
(iv) The accounting
period will be fortnightly.
(v) Cartage
accounts will be paid by electronic transfer within 10 working days following
the end of each accounting period.
(b)
(i) Account
discrepancies relating to the immediately preceding pay period shall be settled
promptly and in no case later than fourteen (14) days from the date of
submission by the Carrier.
(ii) Account
discrepancies relating to other than the immediately preceding pay period shall
be settled within thirty (30) days from the date of submission of the
discrepancy.
(iii) Where,
following settlement of an account discrepancy, an adjustment to payments is
required such adjustment shall be made in the pay period following settlement.
(c)
(i) Where a
Carrier utilises a fuel purchase card supplied by the Contractor, the
Contractor may deduct from the Carrier's cartage payments an amount equal to
the value of the fuel purchased through the card.
(ii) When a
Carrier is overpaid, the Contractor shall supply appropriate details in writing
to the Carrier who shall then immediately authorise the deduction of the amount
of the overpayment from the next payment due to the Carrier. If a large
overpayment is made to a Carrier (e.g. by computer error) then the Carrier must
refund the overpayment to the Contractor immediately.
(iii) No other
deduction can be made from the Carrier's account without the prior written
authority of the Carrier or as otherwise authorised in this agreement.
8. Living Away from
Home Allowance
(a) A Carrier
engaged in work, which precludes him from reaching his usual place of residence
at night, shall receive the benefits and conditions as detailed in the Award.
This sub-clause shall not apply to movements within the
metropolitan areas of Sydney, Newcastle and Wollongong.
(b) Where a
Carrier is required to transfer to a working area which precludes him from
returning to his normal place of residence each night, the Contractor where
possible will provide the Carrier with at least twenty four (24) hours prior
notice of the request.
(c) Where a
Carrier is transferred outside his normal working area, such transfer will be
for a period not exceeding seven (7) days duration or longer by mutual
agreement and will be done from a cyclic transfer roster.
(d)
(i) Transfer
payment in addition will be paid at the rate of ("H") per km or part
thereof that the Carrier is required to travel to and from the directed
transfer location.
(ii) A transfer
docket must be issued by the Contractor to the Carrier prior to departure,
wherever possible, otherwise on arrival at the destination.
(iii) Should
transfer be cancelled or redirected the relevant transfer docket will be
adjusted by the Contractor immediately on the Carrier's return to the plant
from which he was originally transferred.
9. Statutory
Requirements and Insurance
(a)
(i) A Carrier
shall comply with the provisions of all current relevant statutes and
regulations made there under in relation to the use or operation of the truck
and the Carrier shall ensure payment of all lawful fees, licences and taxes in
relation thereto.
(ii) Any variation
in statutory requirements will vary the cartage rate accordingly.
(b) A Carrier
shall arrange insurance cover and keep current whilst working under this
Contract Determination in respect of:
(i) Motor vehicle
comprehensive.
(ii) Motor vehicle
third party/person.
(vi) Worker's
compensation for the permanent driver as well as a casual driver.
(vii) Public
liability cover to the value of $10 million.
(viii) Public liability
for damage by the agitator (extension).
(Note: if the agitator itself is damaged by a negligent
act of the Carrier then the Contractor shall not be liable to compensate the
Carrier)
(vi) Public
liability wrong delivery (extension)
(c) All insurance
policies, registration and license details will be checked by the Contractor
every twelve (12) months to ensure compliance with the provisions of this
Clause. Carriers must produce copies to the Contractor of all necessary
documents to demonstrate that insurances, registration and license requirements
are current and valid.
Any documentation produced by Carriers pursuant to this
clause will be subject to privacy legislation.
10. Loading
(a) Size of Load
(i) The
Contractor has the right to nominate the size of load provided the Carrier has
the right to refuse a load that is beyond the legal capacity of the vehicle or
the rated capacity of the mixer.
(ii) Each Carrier
will be required to submit their truck for weighing at an accredited
weighbridge (or alternatively be weighed by the RTA in the plant or at another
approved site) on a quarterly basis. The Contractor shall bear the expense of
the weighing procedure but the Carrier must comply when directed by the
Contractor to undergo weighing. The truck shall be weighed when fully laden
with water (i.e. when the Wash Down Tank is full of water).
(iii) Each Carrier
shall be loaded wherever possible to the maximum legal capacity of the
Carrier’s truck (based on the density of the concrete mix at the relevant time)
except in the case of a single load or message. Notation: this requirement
shall not apply where loading a truck to its maximum capacity would result in
possible spillage, environmental problems or quality issues.
(b) Loading Order
(i) The initial
daily starting order will be in accordance with a cyclic roster.
(ii) Thereafter
all trucks will be loaded in order of their return to the plant with the
exception of:
(a) Mini mix loads
(less than 3 m³).
(b) Single load or
message greater than the mixer capacity or legal carrying capacity of the truck
next in line.
(c) Trucks with
returned concrete.
(d) Notation: where
the last load of the day or message can be sent in one (1) load so as to avoid
extra cartage cost then the Contractor has the right to nominate a truck to
take the load even though that truck is not the next in line in the roster. If
sending the load in more than one truck will not involve extra cartage cost
then the loading order will not change.
(iii) The
Contractor will operate a fleet of vehicles driven by its employees. This fleet
of company owned vehicles will work in all rosters on the same basis as the
Carrier Fleet.
(iv) The
Contractor's employee driven vehicles will not be preferentially loaded.
(v) The initial
loading time and the initial plant from which such loading shall take place
will be notified by the Contractor to each Carrier before the close of business
on the previous day.
11. Hazardous
Approach to Job Site
(a)
(i) A Carrier
shall have the right to refuse to enter upon ground which he considers unsafe
or extraordinarily hazardous. If a
Carrier does refuse entry and the delivery is completed on that day by other
vehicles without the use of additional equipment then the Carrier that has
refused entry will not be paid for the delivery or return cartage unless the
load has been diverted to another job in which case his delivery to the
alternate location will be paid as if it were a new delivery from the plant
where batched to the alternate location.
(ii) If however
the Carrier has notified the plant of the unsafe or hazardous job site and/or
approach but attempts unsuccessfully to enter, he will be paid the cartage rate
to and from the delivery site even if the delivery is ultimately completed, as
above.
(iii) In all cases
if the Carrier refuses to enter and the delivery is not completed on that day
without the use of additional equipment the Carrier will be paid the total
cartage rate to the job site plus return cartage if the load is returned to the
plant if instructed by the Contractor, unless the load is diverted to an
alternate location in which case the Carrier will be paid in accordance with
5.15 Diverted Loads, hereof.
(iv) If the Carrier
is required to wait for instructions from the plant he will be paid at the rate
of "D" per minute for the total time he is required to wait after he
has notified his plant.
(b) Bogged
Vehicles
(i) Where a
Carrier goes beyond the kerb to complete a delivery and his vehicle becomes
bogged or is otherwise rendered inoperative as a consequence of such attempted
delivery, the Contractor will arrange the services of an experienced salvage
contractor to extricate the vehicle as soon as possible and will bear all costs
for those arrangements.
(ii) It will be
the Contractor's responsibility to ensure that the salvage contractor selected
is covered by the appropriate insurance policy to rectify any damage that the
salvage contractor may cause to the Carrier's vehicle during the extrication
process.
(iii) Waiting time
will be paid to the Carrier from the time the Carrier notifies the plant until
the time of completion of extrication.
(iv) Provided
further that the reimbursement provision shall not apply where the vehicle
becomes inoperative as a direct result of the Carrier's gross negligence or
deliberate actions.
(c) The Carrier
shall be responsible for damage to property or vehicle arising from off-kerb
delivery provided that the Carrier will not have responsibility in situations
where the Carrier has been prevented from exercising due care (e.g. where a
third party has given the Carrier poor directions which resulted in damage) or
where the Carrier has properly notified the customer of the risk of
damage. Damage claims are to be settled
quickly.
12. Availability of a
Suitable Vehicle
(a) It is the
obligation of the Carrier on each working day to personally supply, man,
operate, and keep serviceable, the vehicle.
Any variation to this obligation will require notification from either
party.
(b)
(i) No vehicle
shall be brought into service without prior approval by the Contractor. The
Carrier must advise the Contractor in writing when a vehicle is to be
introduced to the fleet by the Carrier.
(ii) The
Contractor shall have the discretion to refuse to load a vehicle that is
unregistered or obviously defective.
If the vehicle is subsequently shown by the Roads and
Traffic Authority not to be defective the Carrier will be paid as compensation
at the rate "J" per hour or part thereof from the time the load was
refused until the Contractor agrees to load the vehicle, with a maximum of
eight (8) hours per day together with any additional statutory charges.
(c) An
unserviceable vehicle shall be repaired as soon as practicable.
(d) Where a
Carrier is unable to report for work with his vehicle he shall arrange for the
Contractor to be informed at the earliest possible moment of the reason and the
anticipated period of absence.
(e) When a Carrier
is required to submit his vehicle to the Road & Traffic Authority for
annual inspection, he shall inform the Contractor 4 weeks prior to his
registration renewal date or on receipt of his inspection notification
whichever is the earlier. If a
reinspection is required due solely to a defective agitator, then a transfer
fee of "G" per km or part thereof will be paid by the Contractor to
the Carrier for the distance travelled to the nominated inspection station from
the base plant plus any inspection fees payable. In addition the Contractor will pay the Carrier at the rate of
"N" per hour or part thereof for all time lost each day that he is
prevented from his duties pursuant to this Contract Determination to a maximum
of 8 hours each day.
13. Responsibility
for Load
(a) The Contractor
will ensure that the load is batched, with the intent that the quantity of
water required to adjust the slump does not exceed 10% of the total water
required to bring that load up to specification.
(b)
(i) A Carrier
shall ensure that the load is properly mixed as required by the Contractor's
instructions and that the slump of the concrete will be in accordance with
Australian Standard AS 1379:
(a)
|
Less than 60mm.
|
plus or minus 10mm;
|
|
|
|
(b)
|
More than 60 and less than 80mm.
|
plus or minus 15mm;
|
|
|
|
(c)
|
More than 80 and less than 110mm
|
plus or minus 20mm;
|
|
|
|
(d)
|
More than 110mm and less than 150mm
|
plus or minus 30mm;
|
|
|
|
(e)
|
More than 150mm.
|
plus or minus 40mm.
|
(ii) The slump
requirements detailed above must be met by the Carrier before the carrier
leaves the plant to deliver the load in question. The Carrier has the right to
adjust the slump up to the point of discharge in order to ensure the slump is
accurate.
(c) The agitator
drum must be kept turning at all times when it contains concrete other than
kerb maker or low slump concrete.
(d)
(i) A Carrier
shall visually inspect each load prior to leaving the plant and shall advise
the Contractor of any apparent unusual features of the load which may have
occurred due to batching error, plant failure, or contamination.
(ii) Any failure
to report any obvious unusual feature arising from a visual inspection shall be
dealt with in accordance with the Disputes Procedure herein.
(e) When a load is
rejected at a job site because the slump is outside the nominated tolerance
contained herein, or the Carrier has not visually inspected the load prior to
leaving the plant the Carrier will not be paid for the cartage. If the load is subsequently dumped the
Carrier shall refund to the Contractor the materials cost as detailed in the
Bill of Materials (BOM) in circumstances where the slump is so grossly out of
specification (i.e. two times the tolerance) that the Carrier has failed the
duty of care.
(f) The Carrier
is responsible to ensure that all delivery dockets are signed by the customer
and properly completed in all relevant sections. Where this is not done the
Carrier may not be paid for the load.
(g) A Carrier
shall collect money from COD customers for all concrete charges, including the
waiting time. All moneys collected shall be submitted in full (as soon as possible)
to the plant manager or allocator, who shall immediately issue the Carrier with
a receipt.
(h)
(i) The Carrier
shall immediately advise the Contractor where practicable by two-way radio, or
telephone if immediately available where a two-way radio is not provided, when
a COD payment is not collected or a dispute arises between the Carrier and the
customer.
(ii) Carriers are
not required to carry a float for the purposes of provided a change facility.
(iii) The Carrier
will take all due care for any money collected.
(i) In the case
of a delivery of concrete to a kerb-making machine, the Carrier assumes no
responsibility for the slump of the load as it is delivered in an "as
batched" condition. However the Carrier will remain responsible for the detection
of obvious problems such as high slump or complete absence of cement.
(j) Where an
additive is added by the customer or third party after batching, the Carrier is
automatically absolved of any responsibility for the slump.
(k) The concrete
specification as shown on the cartage docket cannot be changed by any party
after batching.
(l)
(i) Where
returned concrete is re-used and is more than 1 1/2 hours old at the time of
reloading, and the return cartage is greater than 0.8 m3 and topped up, the Contractor
will assume full responsibility for the load, thus excluding the Carrier from
his responsibility for the slump of the load.
(ii) The Carrier
will assume responsibility for any breaches in vehicle legal load limits in
relation to this matter as the Contractor has given the Carrier the discretion
to dump any concrete from that topped-up load that the Carrier may deem to
place him in breach of his vehicle's legal load limit.
14. Breakdowns
(a)
(i) Neither the
Contractor or Carrier shall be responsible to each other for any loss resulting
from plant mixer and/or vehicle breakdowns except in the situation set out in
clause 5.11 (Standby Function).
(ii) In the
situation of a plant breakdown sufficient trucks should be transferred to the
plant where the work is being diverted to, in order to provide sufficient
customer service.
(b) In any
situation where either the truck or the mixer breaks down and the Carrier is
carrying concrete then the Carrier must immediately notify the Contractor. The
Contractor shall then assume the responsibility of dealing with the matter
however the Carrier is obliged to co-operate fully with the Contractor in order
to avoid any damage to the mixer. The
Carrier shall not be required to participate in the actual removal of the
concrete from the agitator.
15. Two-Way Radio and
GPS Equipment
(a) The Carrier
shall agree to the installation of two-way radio and GPS equipment on his
vehicle. All equipment shall be
installed by the Contractor's approved technician and such installation shall
be of a professional standard. The
installation shall include all necessary equipment, and the complete
installation shall be undertaken at no cost to the Carrier.
(b) When such
equipment is removed the Contractor shall make good the bodywork.
(c) The Carrier
shall take due care to ensure adequate protection of the equipment.
(d) The equipment
is to be operated and appropriate procedures are to be followed as laid down by
the Contractor.
(e) The Contractor
shall be responsible for the maintenance of the two-way radio and GPS
equipment.
(f) The
Contractor shall provide to the Carrier at no cost the Carrier, all stationery
required to properly operate the GPS equipment and any other monitoring
equipment installed in the vehicle as required by the Contractor.
16. Provision of
Mixer
(a)
(i) The
Contractor shall be responsible for the provision of a mixer with a mixing
capacity of not less than 5 m3 and its safe and proper initial fitting to the
Carrier's vehicle in accordance with the specifications of the respective
manufacturers, including the supply of new bolts, clearance lights, mud flaps
and protective chassis/agitator cover plate acceptable to the Carrier.
(ii) If an
agitator is reasonably required by the Carrier or the Contractor to be removed
at any time for any reason, the total cost of agitator removal and replacement
will be borne by the Contractor.
(b) After the
initial fitting referred to in 16(a) hereof the Carrier shall be responsible
for the mixer being properly secured to the vehicle. The Carrier will be
responsible for all maintenance and replacement of clearance lights, globes and
mud flaps. Mudflaps will be supplied to the Carrier by the Contractor free of
charge.
(c) The Carrier by
mutual agreement may have the U bolts adjusted by a qualified mechanic and the
costs incurred will be paid by the Contractor provided that the Contractor's
workshop shall have the opportunity of undertaking the adjustments. The
appropriate transfer fees will be paid to the Carrier by the Contractor.
(d)
(i) The mixer
shall remain the property of the Contractor and on completion of its use will
be removed by the Contractor at a location nominated by the Contractor at a
time mutually agreed between the carrier and the contractor by in any event,
within forty eight (48) hours.
(ii) The
Contractor will pay to the Carrier a transfer fee of "G" per km or
part thereof to and from the nominated location.
(iii) The Carrier
will be paid at the rate of "N" per hour by the Contractor to allow
for the Contractor's removal of the mixer from the Carrier's vehicle.
(e) Hydraulic
Mixers
The Contractor will provide regular maintenance in
accordance with the mixer manufacturer's recommendations at no cost to the
Carrier. All modification and fitting work is to be done expeditiously and in
any case not longer than 5 working days. The Carrier will be paid by the
Contractor at the rate of "N" per hour to a limit of 8 hours per day.
17. Mixer Care and
Maintenance
(a) A Contractor's
mixer is in the care of the Carrier who shall keep the unit clean and tidy to
the satisfaction of the Contractor.
(b)
(i) A Carrier
undertakes to exercise all reasonable care of the mixer. The mixer shall be thoroughly washed out and
cleaned down as required and surfaces treated in preparation for the next day's
work.
(ii) All cleaning
materials and equipment necessary for cleaning the agitator will be supplied by
the Contractor and shall comply with any and all statutory requirements and
regulations.
(c) The Carrier
shall report any and all apparent maintenance requirements to the Contractor.
(i) The Carrier
shall convey the mixer to the workshop for repairs or maintenance as requested
by the contractor. Such repair or maintenance requirements will be carried out
wherever possible outside normal Carrier's operating hours and all work will be
completed as soon as possible and without delay. If any delay is experienced by
the Carrier for reasons beyond his control, the Carrier will be paid by the
Contractor at the rate of "N" per hour or part thereof to a maximum
of eight (8) hours per day.
(ii) The Carrier
will be paid for transfers to and from the workshop at the rate of
"G" per km or part thereof and the forward and return journey will be
treated separately. If the Carrier is required to wait for his vehicle he will
be paid at a rate of "K" per hour or part thereof. If he is not
required to wait, a means will be provided by the Contractor at the
Contractor's cost to convey the Carrier to his place of residence and return
him to the workshop as when required.
(d) The Carrier
shall be responsible for minor maintenance as described below:
Greasing
Cleaning
(e)
(i) The
Contractor shall be responsible for the removal of hardened concrete build-up
from the inside of the agitator, a process commonly known as de-dagging.
(ii) All
de-dagging will be carried out strictly in accordance with the agreed procedure
and in compliance with all statutory health and safety regulations.
(iii) All
de-dagging work will be conducted outside normal working hours or otherwise by
mutual agreement between the Carrier and the Contractor.
(iv) It shall be
the responsibility of the Carrier to properly wash out the mixer on at least a
daily basis (or as instructed by the Contractor).
(f) The Contractor
shall be responsible for all major maintenance to the mixer.
(g) The Carrier is
responsible for provision of the fuel to run the truck.
(h) The Contractor
is responsible for the provision of oil and grease for the mixer.
(i) The
Contractor's mixer is to be parked only in places approved by the
contractor. The Carrier is not
responsible for any loss or damage to the Contractor's equipment when so
parked. The Carrier is responsible to
make their truck and mixer available for servicing when required by the
Contractor.
(j) A Carrier
will not be responsible for any damage to the mixer whatsoever except in the
case of a Carrier's negligence or deliberate action.
18. Painting and/or
Signwriting of the Mobile Unit
(a) The Contractor
shall arrange for periodical painting and/or sign writing of the mobile unit.
(b)
(i) All painting
(including sandblasting) is to be done expeditiously, weather permitting, in
not more than 8 working days using a quality of paint that is acid resistant
and capable of withstanding the arduous conditions of the industry. The painting will be undertaken by a
recognised truck painting contractor and the standard of finish will be not
less than that provided by tradesmen specialising in this field.
(ii) All necessary
surface preparations and procedures recommended by the paint manufacturers will
be strictly adhered to in order to ensure a professional standard of outcome.
(c) The mobile
units will be repainted at intervals deemed appropriate by the Contractor.
(d) For the purpose
of this clause "mobile unit" shall mean the complete truck and
agitator including all their components and external surfaces without
exception.
(e) For all times
in excess of 8 working days or where a vehicle has to be returned for
repainting or painting repairs, the Carrier will be paid by the Contractor at
the rate of "N" per hour or part thereof with a maximum per day of 8
hours plus all relevant transfer fees, waiting time and the reimbursement of
all travelling costs.
19. Manning
(a) A Carrier when
employing an alternate driver shall engage the driver under terms and
conditions of the Transport Industry (State) Award and shall require the driver
to observe the terms of this Contract Determination in the operation of the
vehicle.
(b) A person operating
the truck of the Carrier pursuant to this Arrangement must first be fully
inducted and approved in writing by the Contractor.
(c) A Carrier
shall be the permanent operator of the vehicle except on a period of absence
approved by the Contractor.
(d) A Carrier
and/or driver shall act in the best interests of the Contractor at all
times. In the event of a dispute
arising in respect of this clause, the procedure in clause 24 Disputes
Procedures shall be observed.
(e)
(i) A Carrier
shall ensure that the driver of the vehicle holds the appropriate class of
driver's licence as required by the Roads & Traffic Authority.
(ii) In the event
that the driver has his licence suspended or cancelled, the Carrier must
immediately inform the Contractor in writing of that fact and that person must
not drive the truck under any circumstances.
20. Uniforms
(a) A Carrier
and/or his driver shall maintain an acceptable neatness of dress and
appearance.
(b)
(i) Where a
uniform is required to be worn by the Carrier, then such uniform shall be
supplied free of charge to the Carrier by the Contractor.
(ii) A
satisfactory quantity of clothing is to be supplied with a minimum of 4 day's
fresh apparel.
(iii) Clothing
issues to Carriers will be on a points system per item. From the date of this Arrangement each
Carrier will be entitled to receive uniforms totalling eight (8) points per
year.
Uniform item points are as follows:
Two shirts (short or long)
|
2 points
|
Two trousers (short or long)
|
2 points
|
Two pairs of overalls
|
4 points
|
Four t-shirts
|
4 points
|
One winter jacket
|
4 points
|
(c) New entrants
into the industry must receive an initial double uniform issue.
(d) Wet weather
and safety gear is to be supplied in accordance with the Award.
21. Amenities
All amenities are to comply with relevant legislation and to
be not less than those enjoyed by an employee under the Award. The appropriate facilities should be
maintained and kept thoroughly clean and hygienic at all times by the
Contractor. Carriers will conduct
themselves in a tidy and appropriate manner.
22. Fleet Size
Subject to the terms of this Contract Determination the
Contractor shall have the absolute discretion to vary its fleet size in any
manner and for any reason.
23. Commitment to
Training
(a) The parties to
this Contract Determination recognise the mutual benefits to be gained through
a greater commitment to training and, accordingly, each party commits itself to
attending appropriate training programs in order to increase the competitive
performance of the Contractor and its Carriers. Carriers would be required only
to attend training programs outside the Contractor's concrete production hours
where mutually agreed.
(b) When training
is undertaken at the request of the Contractor it will be undertaken at no cost
to the Carrier.
(c) If a Carrier
is required to attend such training the Carrier shall be paid at the rate of
"K" per hour or part thereof plus the appropriate penalty rates plus
all allowances covered by the Award plus travelling expenses to and from his
residence at the rate of "L" per km or part thereof.
(d) A prospective
Carrier shall spend a minimum of 2 weeks training to operate the mixer, slump,
etc., including a training period of one day in the contractor's Quality
Control Laboratory under the Contractor's supervision followed by one day field
testing under the supervision of the Contractor's testers.
(e) All Carriers
engaged pursuant to this Arrangement must obtain Certificate 3 in Transport and
Distribution (Road Transport) through an approved training provider. All
carriers must be signed up to a course to complete this certificate training
prior to 1 November 2005.Thereafter new entrants to the Hanson fleet must sign
up to the course when they commence.
24. Disputes Procedure
(a) It is
understood and accepted by all parties to this Contract Determination that work
shall continue normally during all negotiations and any necessary proceedings.
(b) When there is
a disagreement, the Carrier shall attempt to resolve the matter by negotiating
with the Contractor or his representative on site.
A Carrier elected as a Yard Delegate shall upon
notification to the Contractor by the union be recognised as the accredited
representative of the union. Yard delegates and Executive Committee members
will be provided with reasonable access to and use of a telephone at no cost
for the purpose of union matters.
(c) Where the
matter is not resolved, the Yard Carrier Delegate shall attempt to resolve the
matter by negotiation with the Contractor or his representative on site. Where applicable the Carrier's executive
delegate or his representative may be party to further negotiations with the
Contractor.
(d) If the matter
remains unresolved the Chairman of the Industry concrete section or his
representative of the Union along with an official of the Union and the
Company's executive delegate shall be party to continued negotiations with the
Contractor.
(e) If the matter
remains unresolved the Secretary, Assistant Secretary or the representative of
the Union may be party to continued discussions/negotiations with the relevant
representatives of the Contractor.
(f) If the matter
is unresolved the matter will be notified to the Industrial Relations
Commission of New South Wales.
25. Rostering
(a) The Contractor
undertakes that it will operate rosters to ensure that plant utilisation for
Carriers is effective for all parties.
(b) The Contractor
will not roster-off a Carrier simply because he is earning in excess of the
average plant utilisation applicable during the relevant period.
(c) Those rosters
will include:
(i) Daily start
cyclic roster
(ii) Daily
transfer cyclic roster
(iii) Period (not
exceeding one month) transfer cyclic roster.
(iv) Roster-off
roster (where there are vehicles surplus to customer requirements) as per the
agreed Business Rules.
(d) The Contractor
shall regularly consult with Carrier representatives to ensure the utilisation
system is operating effectively.
(e) If it is found
that a Carrier or Carriers are experiencing low utilisation then the Contractor
may move those Carriers to other locations with a view to improving their
utilisation
26. Plant Stored
Carrier's Equipment
The Contractor will provide sufficient space for the safe
storage of equipment that is reasonably necessary to assist in the efficient
and effective running of the Carrier's cartage business.
27. Business
Viability
(a) Where the
available work at a plant falls below a level, which is viable for the Carrier
or Carriers at that plant, then the Contractor may transfer the Carrier or
Carriers to another plant.
(b) If a Carrier
refuses to accept a transfer in the circumstances of subclause (a) hereof then
the matter shall be dealt with through the Disputes Procedure. In all
circumstances the Carrier shall remain free to resign from the fleet or sell
his contract subject to the terms of this Contract Determination.
28. Occupational
Health and Safety
(a) The Contractor
will establish a Safety Committee with a maximum of two Carriers representatives
elected to the Committee.
(b)
(i) The
Contractor will pay each elected Carrier's safety officer for any and all time
such Carrier spends in relation to their duties as safety officers as requested
by the Contractor.
(ii) Such Carrier
will be paid promptly but in any case not later than 14 working days from the
date their time is expended.
(iii) In addition,
the safety officer will be paid by the Contractor at the rate of "K"
per hour or part thereof plus the Award penalty rate travelling time to a
maximum of half hour each way plus "L" per km or part thereof that he
is required to travel from his base plant or place or residence whichever is
the greater, to and from the respective location requiring his presence.
29. Environment
Protection and Pollution Control
(a) Operational
Procedures
The Contractor will provide the Carrier with a written
procedure relating to the delivery of concrete. It is the Contractor's responsibility to ensure that this
procedure complies with all requirements of the relevant Act with respect to
environment protection and pollution control. It is the Carrier's
responsibility to comply with the Contractor's reasonable written procedures.
(b) Contractor's/Carrier's
Liability
The Contractor will indemnify the Carrier against all
claims for cost, damages and/or legal expenses and any further liabilities that
may arise whilst performing his duties as a Contractor's Carrier in accordance
with the Contractor's operational procedures or if none are available, the
usual custom and practice save for liability arising as a direct consequence of
the Carrier's gross negligence or deliberate action.
30. Contractor's
Subsidiary Companies
The Contractor undertakes that it will not use any of its
subsidiaries or related corporations to restrict or reduce the optimum
utilisation of its contract carrier fleet.
Schedule A
RISE AND FALL
|
Cost
|
Cost
|
Description/Explanation
|
|
Elements
|
Values
|
|
|
|
$
|
|
SECTION A: FIXED COSTS:
|
|
|
|
|
|
|
|
Truck & insurance
costs
|
|
|
|
|
|
|
|
Truck Registration (6 wheeler)
|
1,182.00
|
1,182.00
|
NSW registration cost for six wheeler
|
CTP Insurance
|
1,674.00
|
1,674.00
|
CTP cost
|
|
|
|
|
Current Truck Valuation =
|
130,035.00
|
|
GST Excl cost of new Iveco/Mack six
|
Truck insurance rate
|
2.85%
|
|
wheeler concrete truck
|
Truck insurance rate is for a 40%
|
3,706.00
|
3,706.00
|
Comprehensive insurance rate with 40% no
|
no claim as average
|
|
|
claim bonus
|
|
|
|
Cost of comprehensive insurance based on
|
|
|
|
insurance rate and value of new truck
|
|
|
|
|
Public Liability (incl agi extension,
|
393
|
393.00
|
Public liability insurance cost from Aussie,
|
wrong delivery) insurance
|
|
|
with a $10m limit.
|
|
|
|
|
Workers' compensation insurance%
|
9.625%
|
|
NSW workers compensation insurance
|
|
|
|
rate for concrete truck employees
|
Labour Costs
|
|
|
|
Owner Driver Labour
Costs
|
|
|
|
Driver
|
|
|
|
Base award Rate
|
13.86
|
|
Award rate for Mixed Enterprises state award
|
Working Weeks
|
48.00
|
|
Number of weeks truck is available with LOD
|
|
|
|
as driver
|
|
|
|
|
Normal Time
|
25,280.64
|
25,280.64
|
Calculation of normal time weeks @38hrs/
|
|
|
|
week, working weeks and award rate
|
Slump Allowance
|
17.26
|
|
Award rate for slump allowance(weekly rate)
|
Slump allowance pa
|
828.48
|
828.48
|
Slump allowance pa based on allowance
|
|
|
|
and weeks available
|
|
|
|
|
Superannuation %
|
9%
|
|
Statutory superannuation contribution rate
|
Superannuation on normal time
|
2,349.82
|
2,349.82
|
Superannuation cost pa on normal time
|
earnings
|
|
|
earnings and slump allowance
|
|
|
|
|
Leave Loading %
|
17.5%
|
|
Statutory leave loading factor
|
Leave loading pa
|
368.68
|
368.68
|
Leave loading based on four weeks
|
|
|
|
leave, 38hrs/week, and base award rate
|
Long Service Leave
|
456.46
|
456.46
|
Long Service leave cost based on 13 weeks
|
|
|
|
for 15 years service, 38hrs per week and base
|
|
|
|
award rate
|
|
|
|
|
Union Picnic Day
|
105.34
|
105.34
|
Picnic day cost, based on 7.6 hr day at base
|
|
|
|
award rate
|
|
|
|
|
Workers Compensation
|
2,602.56
|
2,602.56
|
Workers compensation cost based on workers
|
|
|
|
compensation cost rate %, and earnings
|
|
|
|
(normal time, slump, leave
|
|
|
|
loading, long service leave and picnic day)
|
|
|
|
|
Casual Driver Labour
Costs
|
|
|
|
RDO's assumed worked by a casual
|
3.00
|
|
Number of RDO's
|
(days)
|
|
|
|
Casual hours per day
|
7.60
|
|
|
Concrete Driver - base wage rate
|
14.44
|
|
Base rate $/hr for concrete driver based on
|
|
|
|
T I State Award
|
Casual loading
|
15%
|
|
Casual employee loading factor
|
Casual rate per hour
|
17.99
|
|
Casual employee hourly rate based on
|
|
|
|
casual loading factor on concrete driver wages
|
|
|
|
|
Casual Wages for RDO
|
410.17
|
410.17
|
|
Slump Allowance
|
17.26
|
|
|
Slump allowance pa
|
|
-
|
|
Annual Leave
|
2.00
|
|
Number of weeks casual is required to replace
|
|
|
|
LOD
|
Casual hours
|
40.00
|
|
Hours per week a casual works
|
Normal Time
|
1,439.19
|
1,439.19
|
Cost of casual based upon casual hourly rate,
|
|
|
|
weeks required and hours worked per week
|
|
|
|
|
Slump Allowance (2 weeks)
|
34.52
|
34.52
|
Slump allowance to casual based on slump
|
|
|
|
allowance rate and number of weeks casual
|
|
|
|
is required
|
Overtime
|
|
|
|
|
|
|
|
Owner Driver Labour Costs
|
|
|
|
Time & half hours per week
|
5.50
|
|
Number of hours worked by LOD at time
|
|
|
|
& half
|
double time hours per week
|
4.00
|
|
Number of hours worked by LOD at double
|
|
|
|
time
|
Overtime pa
|
10,810.80
|
10,810.80
|
Overtime cost based on over time hours
|
|
|
|
and base award rate
|
|
|
|
|
Total Labour Costs
|
|
44,686.64
|
Total Labour related cost
|
|
|
|
|
Other Fixed Costs
|
|
|
|
Depreciation
|
|
|
|
Residual %
|
30%
|
|
Residual value of truck at end of life of
|
|
|
|
contract. % of truck value
|
Initial age of truck (average)
|
2.00
|
|
Age of truck (Yrs) at start of contract
|
Life of contract
|
9.00
|
|
Period of contract remaining (Yrs)
|
Depreciation pa
|
8,274.95
|
8,274.95
|
Depreciation of truck pa. Annual value
|
|
|
|
calculated on the decrease in value of the
|
|
|
|
truck (initial value less residual) over the life
|
|
|
|
of the contract
|
|
|
|
|
Administration
|
2,500.00
|
2,500.00
|
Cost estimate for administration
|
|
|
|
|
Incorporation establishment fee
|
175
|
175.00
|
Amortised cost estimate of company
|
|
|
|
incorporation costs over a 10 year period
|
Statutory postage and
|
267
|
267.00
|
Cost estimate for postage & misc costs
|
miscellaneous expenses
|
|
|
|
Interest/profit
|
6500
|
6,500.00
|
Agreed fixed profit component in LOD
|
|
|
|
contract
|
|
|
|
|
TOTAL FIXED COSTS
|
|
69,358.60
|
|
|
|
|
|
Utilisation rate
|
6000
|
|
Utilisation rate (M3 pa) to calculate the
|
|
|
|
load fee
|
Load Fee
|
|
11.56
|
Load fee based on total fixed costs
|
|
|
|
divided by utilisation
|
SECTION B: RUNNING COSTS
|
|
|
|
|
|
|
|
Utilisation for running costs
|
6000
|
|
Utilisation rate for calculation of running
|
|
|
|
costs - fixed for the duration
|
|
|
|
|
Tyres
|
|
|
|
|
|
|
|
Steer tyre cost
|
538
|
|
Cost of a steer tyre (each) based upon the
|
|
|
|
retail price of a Dunlop SP370.
|
Steer tyres per year
|
2
|
|
Number of steer tyres requiring replacement
|
|
|
|
each year
|
|
|
|
|
Steer cost pa
|
1076
|
1,076.00
|
Cost of steer tyre replacements pa, based on
|
|
|
|
cost per tyre and number of tyres replaced
|
Recap tyre cost ea
|
145
|
|
Cost of a recap tyre
|
Recap tyres per year
|
10
|
|
Number of recap tyres replaced each year
|
Recap cost pa
|
1450
|
1,450.00
|
Recap tyre replacement cost based on cost
|
|
|
|
per tyre and number of tyres replaced
|
|
|
|
|
Puncture cost ea
|
28.86
|
|
Cost of puncture repair
|
Punctures pa
|
16
|
|
Number of punctures each year
|
Puncture cost pa
|
461.76
|
461.76
|
Cost of puncture repairs each year based
|
|
|
|
upon cost per puncture and number of
|
|
|
|
punctures occurring pa.
|
|
|
|
|
Cases cost ea
|
95
|
|
Cost of Cases each
|
Cases pa
|
5
|
|
Number of cases required each year
|
Cases cost pa
|
475
|
475.00
|
Cost of cases each year based on cost per
|
|
|
|
case and number of cases required each year
|
|
|
|
|
Disposal of cases ea
|
10.5
|
|
Case disposal cost per case
|
Disposals of cases pa
|
5
|
|
Number of case disposed of per year
|
Total cost of disposals pa
|
52.5
|
52.50
|
Cost of disposals based on cost per case and
|
|
|
|
number per year
|
|
|
|
|
Total tyre cost
|
|
3,515.26
|
|
|
|
|
|
Repairs &
maintenance
|
|
|
|
|
|
|
|
Maintenance cost
|
5980
|
5,980.00
|
Annual cost of maintenance
|
Major Repairs provision
|
2500
|
2,500.00
|
Annual allowance for major repairs, based on
|
|
|
|
$22,500 over contract life
|
|
|
|
|
CPI @ start of contract
|
145
|
|
CPI at start of contract
|
CPI @ present date
|
145
|
|
CPI at review date
|
|
|
|
|
Total repairs & maintenance
|
|
8,480.00
|
|
|
|
|
|
Fuel
|
|
|
|
|
|
|
|
Avg Lead
|
8.58
|
|
Average lead of LOD fleet
|
Avg Load
|
5.1
|
|
Average load size for LOD fleet
|
Fuel usage rate
|
1.4
|
|
Fuel usage km/litre, based on Cummins 265
|
Fuel cost (Gross)
|
119.8
|
|
Cost per litre of distillate - based on
|
|
|
|
benchmark rate
|
Fuel Cost - Rebate
|
18.51
|
|
Rebate $/litre
|
Fuel cost - net
|
101.29
|
|
Net cost per litre of distillate
|
Number of loads pa
|
1,176
|
|
Number of loads pa, based on utilisation
|
|
|
|
and average load size
|
Distance travelled pa
|
20,188
|
|
Distance travelled based on number of
|
|
|
|
loads and average lead
|
Fuel consumed (litres) pa
|
14,420
|
|
Fuel consumed per year based on
|
|
|
|
kilometres travelled and fuel usage rate
|
|
|
|
|
Total fuel cost
|
14,606
|
14,606.19
|
Annual fuel cost based on fuel consumed pa
|
|
|
|
and net fuel cost per litre
|
Profit
|
7,000
|
7,000.00
|
Agreed variable profit element
|
|
|
|
|
Total Running Costs
|
|
33,601.45
|
Total running costs
|
|
|
|
|
Metre Kilometres travelled
|
51480
|
|
Total metre kilometres travelled
|
|
|
|
(utilisation x average lead)
|
|
|
|
|
Running cost per m3/kilometre
|
|
0.65
|
Running rate (running costs divided by total
|
|
|
|
metre kilometres)
|
Surcharges
|
|
2.67
|
Agreed rate per cubic metre for transfers and
|
|
|
|
surcharges.
|
|
|
|
To be varied by reference to the CPI
|
|
|
|
|
Overtime Surcharge
|
|
|
|
|
|
|
|
Overtime Surcharge - time & half
|
0.15
|
|
Number of time & half overtime hours
|
per 100m3
|
|
|
worked per week for each additional
|
|
|
|
100m3 above 6,000m3
|
Overtime Surcharge - double time
|
0.15
|
|
Number of double time overtime hours
|
per 100m3
|
|
|
worked per week for each additional
|
|
|
|
100m3 above 6,000m3
|