Building
and Construction Industry (State) Award
INDUSTRIAL RELATIONS
COMMISSION OF NEW SOUTH WALES
Review of Award pursuant to Section 19 of the Industrial
Relations Act 1996.
(No. IRC 814 of 2007)
Before Mr Deputy
President Sams
|
6 June 2008
|
REVIEWED
AWARD
1. Delete
subclause 6.6 of clause 6, Area, Incidence and Duration, of the award published
31 August 2001 (327 I.G. 279), and insert in lieu thereof the following:
6.6 The changes made
to the award pursuant to the Award Review pursuant to section 19(6) of the Industrial
Relations Act 1996 and Principle 26 of the Principles for Review of Awards
made by the Industrial Relations Commission of New South Wales on 28 April 1999
(310 I.G. 359) take effect on and from 6 June 2008.
This award remains in force until varied or rescinded,
the period for which it was made already having expired.
2. Delete the
table appearing in subclause 25.41, Table of Special Rates, of clause 25,
Special Rates, and insert in lieu thereof the following:
25.4.1 Table of Special
Rates
Item No.
|
Clause No.
|
Description
|
Amount
|
|
|
|
$
|
1
|
25.1
|
Insulation Work
|
0.66 p/h
|
2
|
25.2
|
Hot Work
|
|
|
|
Between 46°
and 54°
|
0.53 p/h
|
|
|
Beyond 54°
|
0.66 p/h
|
3
|
25.3
|
Cold Work
|
0.53 p/h
|
4
|
25.4
|
Confined Space
|
0.66 p/h
|
5
|
25.6
|
Explosive Powered tools
|
1.26 p/d
|
6
|
25.7
|
Wet Work
|
0.53 p/h
|
7
|
25.8
|
Dirty Work
|
0.53 p/h
|
8
|
25.9
|
Towers Allowance
|
|
|
|
Work above 15 metres
|
0.53 p/h
|
|
|
Each further 15 metres
|
0.53 p/h
|
9
|
25.10
|
Toxic Substances
|
|
|
|
Using toxic substances
|
0.66 p/h
|
|
|
In close proximity
|
0.53 p/h
|
10
|
25.12
|
Materials containing asbestos
|
0.66 p/h
|
11
|
25.13
|
Furnace Work
|
1.40 p/h
|
12
|
25.14
|
Acid Work
|
1.40 p/h
|
13
|
25.16
|
Cleaning down brickwork
|
0.48 p/h
|
14
|
25.17
|
Bagging
|
0.48 p/h
|
15
|
25.18
|
Bitumen Work
|
0.66 p/h
|
16
|
25.19
|
Plaster or composition spray
|
0.53 p/h
|
17
|
25.20
|
Slushing
|
0.53 p/h
|
18
|
25.21
|
Dry polishing of tiles
|
0.66 p/h
|
19
|
25.22
|
Cutting tiles
|
0.66 p/h
|
20
|
25.23
|
Second hand timber
|
2.09 p/d
|
21
|
25.24
|
Roof repairs -Employees other
than slaters and roof tilers
|
0.66 p/h
|
22
|
25.24(i)
|
Roof Repairs - Slaters and
roof tilers
|
|
|
|
Height over 15 metres
|
0.48 p/h
|
|
25.24(ii)
|
35° pitch
|
0.66 p/h
|
|
|
40° pitch
|
0.97 p/h
|
23
|
25.25
|
Computing quantities
|
3.84 p/d
|
24
|
25.26
|
Height work - painting
tradespersons
|
0.48 p/h
|
25
|
25.27
|
Height work - bridge and wharf
carpenters
|
|
|
|
8 metres from ground, deck,
etc.
|
0.53 p/h
|
|
|
Each additional 3 metres
|
0.10 p/h
|
26
|
25.28
|
Grindstone Allowance
|
5.65 p/w
|
27
|
25.30
|
Certificate Allowance
|
0.53 p/h
|
28
|
25.31
|
Spray Application - painters
|
0.53 p/h
|
29
|
25.32
|
Cutting bricks
|
0.66 p/h
|
30
|
25.33(a)
|
District Allowances
|
|
|
|
Districts west and north
|
0.78 p/d
|
|
|
Western Division
|
1.28 p/d
|
31
|
25.33(b)
|
District Allowances
|
|
|
|
NSW border to Dalgety
|
1.28 p/d
|
32
|
25.33(c)
|
District Allowances
|
|
|
|
Road and bridge construction
and repair
|
0.41 p/d
|
33
|
25.34
|
Pneumatic tools - stonemason
|
2.89 p/d
|
34
|
25.35
|
Asbestos Eradication
|
1.78 p/h
|
35
|
25.36
|
Laser safety officer
|
2.19 p/d
|
36
|
25.37
|
Illawarra road and general
construction
|
0.53 p/h
|
37
|
25.38
|
Suspended Perimeter Work
Platform
|
0.81 p/h
|
38
|
25.39
|
Labourers on refractory
brickwork
|
3.96 per call back
|
39
|
25.40
|
First Aid Allowances
|
|
|
|
Minimum qualification
|
2.26 p/d
|
|
|
Higher qualification
|
3.56 p/d
|
P.
J. SAMS D.P.
____________________
Printed by
the authority of the Industrial Registrar.